Is my money protected if I buy off-plan in Italy?

Yes, if you are a private individual buying from a builder. For a project whose building permit was requested after 16 March 2019, Legislative Decree 122/2005 gives you three safeguards at once: a guarantee from a bank or insurer on the money you pay before the deed, a preliminary contract signed in front of a notary, and a 10-year insurance policy against serious defects. You cannot waive any of them, even for a discount: a clause saying otherwise is void (article 5).

The risk is simple: you pay for a home that does not exist yet, and the builder fails before handing it over. Italian law answers with a guarantee, a notary and a policy.

Italian legal sources abbreviate the whole framework to TAIC (protection of buyers of properties to be built). You will meet the acronym there.

In short

  • Who is covered: a private individual, buying from a builder who sells as a business or from a building cooperative.
  • What is covered: a property whose building permit has been requested and which is not yet far enough along for a certificate of habitability (agibilità).
  • The guarantee: issued by a bank or an insurer, sized to everything you pay before the deed, with no deductible. Without it, the contract is void, and only you can say so.
  • The preliminary contract: a public deed or a notarised private agreement, with the guarantee details written into it.
  • The policy: a 10-year indemnity policy, handed over at the deed, running from the end of the works.
  • The dates that matter: the 2019 rules apply when the permit was requested after 16 March 2019; the standard policy model of Decree 154/2022 does not apply to building titles issued before 5 November 2022 (article 389 of Decree 14/2019).

Does the law cover my purchase?

Three tests, all in article 1 of the decree.

The buyer is a natural person. A company is not covered. The definition also reaches a purchase made for a first-degree relative, such as a child, and property leasing contracts that lead to a later transfer.

The seller is a builder. The decree says an entrepreneur or a building cooperative. It makes no difference whether the builder works directly or through contractors.

The property is "to be built". The decree defines it as a property for which a building permit has been requested and which is still to be built, or not yet far enough along for the certificate of habitability. Two consequences follow. A building far enough along to obtain its certificate of habitability is outside the decree. So, by the same definition, is a plot for which nobody has yet requested a permit. Ask early when the permit was requested, and ask for its number.

The date also decides which version of the rules you get. Under article 5, the 2019 changes (notarised preliminary, standard models, the link between policy and guarantee) apply to projects whose building title was requested or filed after the decree that introduced them came into force. The Italian notaries' guide gives that date as 16 March 2019. The guarantee and policy rules themselves cover properties whose permit was requested after the decree came into force on 21 July 2005 (article 5). For an older project, ask the notary which regime governs your contract.

What does the builder's guarantee cover?

The guarantee (fideiussione) must be issued by a bank or an insurer (article 3), and the builder must deliver it when the contract is signed, or earlier (article 2). If it is missing, the contract is void, but only you can invoke that.

Its amount corresponds to the sums the builder has collected and the sums it is due to collect, under the contract, before the transfer of ownership. Two exclusions are written into article 2: amounts a lender is to pay directly, and public grants that already carry their own guarantee.

What the guarantee returns is narrower: the sums the builder has actually collected, plus legal interest up to the moment of the crisis (article 3).

Payments are usually staged, so some of your money is not yet paid when you sign. The civil code allows a guarantee for future obligations if it states a maximum amount (article 1938), and the ministerial model, Decree 125/2022, requires that ceiling and says there is no deductible.

Example. A flat at €400,000: €40,000 at the preliminary, €200,000 in instalments as the works progress, €160,000 at the deed. The guarantee has to be sized to €240,000, the sums due before the transfer. The €160,000 is paid at the deed itself. These amounts are invented for illustration. If your lender pays part of the price directly, that part is excluded from the guarantee.

When can I call on the guarantee?

Two situations (article 3).

The builder is in crisis. The decree treats the crisis as having occurred on the date of one of these events: an attachment on the property is recorded; a bankruptcy judgment or compulsory liquidation order is published; the builder files for composition with creditors; or an insolvency judgment is published.

It is not an automatic exit. After an attachment, you must first tell the builder that you withdraw. After the other events, the guarantee can be called only if the official running the insolvency procedure has not announced that the procedure takes over the preliminary contract.

The policy is not delivered. If the notary certifies that no compliant policy was received by the date of the deed, and you have told the builder you withdraw, you can call the guarantee (articles 3 and 4).

The mechanics are strict. Your claim must be in writing, sent by registered post with proof of receipt (raccomandata A/R) or, under the standard model, by certified email (PEC), together with documents showing what you paid. The guarantor must pay within 30 days, and if it is late it also owes your necessary costs, with interest. The guarantee must waive the guarantor's right to pursue the builder first, and an unpaid premium cannot be used against you.

Why does the preliminary contract go before a notary?

Because the 2019 reform says so. Article 6 requires the preliminary contract to be an atto pubblico (a public deed drawn up by a notary) or a scrittura privata autenticata (a private agreement whose signatures a notary authenticates). The notary's job is to check, before you are committed, that the guarantee exists and follows the model.

Article 6 also fixes what the contract must say. Among other things:

  • the technical features of the building: structure, foundations, walls, floors, roof, windows and doors, systems;
  • the maximum deadlines for the works;
  • the price, the schedule and how payments are made: bank transfers or deposits into accounts in the builder's name, so each payment can be proved;
  • the guarantee details and a statement that it follows the standard model;
  • any mortgages or encumbrances on the property;
  • the permit details.

Two documents must be attached: the specification of materials and finishes, and the design drawings of your unit and its shared parts.

The models are set by ministerial decrees. The standard guarantee is Decree 125/2022, published on 24 August 2022. The standard policy is Decree 154/2022, published on 21 October 2022. A guarantee signed before 23 September 2022 keeps its effect until it expires.

A notarised preliminary is also recorded in the property registers (article 2645-bis of the civil code). When the final deed follows, it prevails over mortgages and entries recorded against the builder after the preliminary. The effect lapses if the final deed is not recorded within one year of the agreed date, and in any case within three years. Article 6 expressly saves Royal Decree 499 of 1929, the law of the Libro fondiario, the land register used in Trieste. See our guide to it and ask the notary how your preliminary will be recorded.

This is not the ordinary compromesso used when buying an existing home. For that process, see how buying a home in Italy works.

What does the 10-year policy cover?

The builder must take out an indemnity policy and hand it over at the rogito, the final notarial deed that transfers ownership (article 4). The policy runs for 10 years from the end of the works. It covers material and direct damage to the building, including damage to third parties, for which the builder is liable under article 1669 of the civil code. That means total or partial collapse, or serious construction defects, from the ground or from the construction, appearing after the final contract.

Article 1669 is the legal yardstick. Under it, the defect must appear within ten years of completion and be reported within one year of its discovery. "Serious defect" is a legal category, not a synonym for anything that annoys you. Ask for the policy's claims procedure in writing.

The deed must state the policy details and say that it conforms to the ministerial model. The guarantee stops working when the guarantor receives a copy of that deed (article 3). Under the model of Decree 125/2022 it also stops if the final deed is signed even though the policy is missing.

What about the builder's mortgage?

Builders often finance the project with a loan secured on the whole building. Article 8 stops the notary from signing the sale deed unless the loan has been divided into shares per unit, or a title for cancelling or dividing the mortgage has been put in place. Ask the notary to confirm this before the deed. Our guide to signing the Italian deed explains what happens in the room.

What should I ask the builder before paying anything?

Put these in writing and early:

  1. When was the building permit requested, and what is its number? It tells you which rules apply.
  2. Who issues the guarantee, and what maximum amount does it state? Compare the amount with your payment schedule.
  3. When will I have the guarantee? The builder must deliver it when the preliminary is signed, or earlier (article 2).
  4. Is it on the ministerial model? The preliminary must say so.
  5. What is the mortgage position on the building? Ask how the loan will be divided.
  6. Who is the insurer for the 10-year policy, and when will I see the draft?

A builder who answers these quickly is behaving normally. One who finds them awkward has told you something useful.

What if the property is sold at auction?

Article 9 gives a buyer who has taken delivery and lives there as a main home, or for a spouse or first-degree relative, a right of pre-emption at the auction price, even after calling the guarantee. It must be exercised within 10 days of the notice.

What this guide does not tell you

The decree has more detail than a guide can carry, and the date of the permit changes what applies. The notary handling your purchase should confirm which rules govern your contract, what the guarantee says, and whether the policy matches the model. Whether to buy is a separate question: it depends on the builder, the price and your finances.


This article is for general information and is not legal advice. For your specific case, write to richieste@triestevillas.com or WhatsApp +39 331 8940822.

Sources
  1. D.Lgs. 122/2005 (artt. 1-6, 8-9), Normattiva
  2. D.Lgs. 14/2019 art. 389, Normattiva
  3. D.M. Giustizia 6 giugno 2022, n. 125, Normattiva
  4. Art. 1669 codice civile, Brocardi
  5. Art. 2645-bis codice civile, Brocardi
  6. Notariato – Acquisto in costruzione
  7. Federnotizie – Preliminare trascritto: le nuove regole
  8. Federnotizie – Modifiche al D.Lgs. 122/2005
  9. Federnotizie – TAIC: i modelli standard
  10. Regione FVG, Tavolare: Cos'è il libro fondiario
  11. D.M. 125/2022, Allegato A (GU n. 197 del 24/08/2022)

Written with AI and checked against the sources by the TriesteVillas editorial team. How we use AI →

This is an overview, not legal or tax advice: rules change and cases differ. Your notaio and commercialista have the final word — and TriesteVillas walks you through every stage in person. richieste@triestevillas.com · +39 331 8940822 (WhatsApp).

Looking for a home?

Homes in Trieste, Friuli-Venezia Giulia and across the border, with the real numbers on costs and taxes.

Browse the properties →

Still curious

Ask the question this page didn't answer.

Answers by Claude, TriesteVillas' AI concierge. It can be wrong — and says so. Conversations are recorded and can be reread by our team.

Keep reading

From the portfolio

The homes for sale closest to what this guide covers.